Applied Digital has closed a $300 million senior secured bridge facility to support construction of Delta Forge 1, its AI data-center campus in Louisiana. The November 23 announcement identifies the arranger only as a leading global financial institution and does not name the lender.
A delayed-draw bridge loan
The financing is a delayed-draw term loan with a 364-day maturity, priced at SOFR plus 300 basis points. It is secured by project assets and can be prepaid without a premium. The company says draws depend on conditions that include construction milestones, lender consents, financial covenants and regulatory approvals, including state approval of electricity rates.
Commitment versus cash received
That structure means the $300 million is facility capacity under an executed loan arrangement. The announcement does not state that the full sum has been drawn or received as cash. Applied Digital also expects to seek further financing to complete construction at Delta Forge 1.
Funding Delta Forge 1
The campus is backed by a long-term lease with an unnamed US tier-one, investment-grade hyperscaler, according to the company. Applied Digital develops and operates large AI computing sites, combining electrical infrastructure, liquid cooling and connectivity for demanding computing workloads. Its model relies on long-term leases rather than consumer cloud subscriptions.
Infrastructure financing
Co-founder Wes Cummins serves as chairman and CEO, alongside president and co-founder Jason Zhang. This is project-backed debt for an operating AI infrastructure business, separate from an equity financing or a new company valuation. Construction progress and satisfaction of the draw conditions will determine access to the committed capital.
Sources
https://ir.applieddigital.com/news-events/press-releases/detail/164/applied-digital-announces-300-million-senior-secured
https://www.applieddigital.com/leadership
https://www.applieddigital.com/about
https://www.applieddigital.com/about
Image: Applied Digital; official photograph of a data-center facility under construction. Black-and-white adaptation by Very Frontier.